If you find this case helpful and would like to access more cases like this, please subscribe to LawPavilion PRIME here
CASE TITLE: WECO ENGINEERING AND CONSTRUCTION CO. LTD v. DUFAN (NIG) LTD & ANOR (2019) LPELR-47211(CA)
JUDGMENT DATE: 4TH APRIL, 2019
PRACTICE AREA: LAW OF CONTRACT
LEAD JUDGMENT: SAMUEL CHUKWUDUMEBI OSEJI, J.C.A.
SUMMARY OF JUDGMENT:
INTRODUCTION
This appeal borders on Contract.
FACTS
This is an appeal against the judgment of the Federal High Court, sitting in Benin Division and delivered on the 23rd day of June 2006. Wherein the plaintiff’s (1st Respondent) claim was granted. The Appellant and the 2nd Respondents were the 1st and 2nd Defendants respectively at the Federal High Court while the 1st Respondent was the plaintiff.
The facts as per the plaintiff’s (1st Respondent) case was that it was the owner of the houseboat known as DUFAN VI which was hired by the Appellant on 26/10/1994. The terms of the hire contract were reduced into writing in a comprehensive agreement signed by the parties. By the said contract, the Appellant was to return the Houseboat (DUFAN VI) to the 1st Respondent at the expiration of the hire contract which was for a period of two months from the date of commencement. The said houseboat was stationed in Warri Delta State where the Appellant took possession of same and moved it to Port-Harcourt, Rivers State where unfortunately it got submerged. The Houseboat upon eventual recovery from the water had remained in the custody of the Appellant.
The 1st Respondent complaint was that the said Appellant has refused or failed to return the houseboat or pay the rents accruing from it, hence an action was instituted in the Federal High Court whereby in paragraph 39 of the 2nd Amended Statement of claim the 1st Respondent as claimed against the Appellant as follows:
“WHEREFORE, the plaintiff’s claim against the 1st Defendant as follows:
(a) The sum of N20,000,000.00 (Twenty Million Naira) being the cost of the 32 rooms House-Boat DUFAN VI and Generator Barge hired out by the plaintiff to the 1st Defendant at Warri within the Jurisdiction of this Honourable Court vide an agreement dated 26th day of October, 1994 executed between the Plaintiff and the 1st Defendant or in the Alternative a return of the said House-Boat and Generator/Barge in perfect condition as stipulated in clause 5 of the agreement dated 26th day of October, 1994.
(b) The sum of N1,800,000.00 (One Million Eight Hundred Thousand Naira) being the hire fee due and payable on the said 32 rooms House-Boat DUFAN VI and Generator/Barge but which said sum has not been paid by the 1st Defendant to the Plaintiff till date from the 16th day of November, 1994 to the 15th day of March, 1995.
(c) The sum of N20,000.00 (Twenty Thousand Naira) per day on the 32 room House-Boat DUFAN VI commencing from the 14th day of February 1995 till the date or return of the said generator House and canopy or judgment.”
Based on an application by the Appellant the 2nd Respondent was joined as 2nd Defendant by the Court on 22/4/1997.
The 1st Defendant also claimed against the Plaintiff as follows:
(a) The sum of N6,672,810.00 (Six Million Six Hundred and Seventy-two Thousand, Eight Hundred and Ten Naira) as special damages for breach of contract and loss suffered by the 1st Defendant as a result of the sinking of the House Boat/vessel, the particulars of which are set out in paragraph 45 above.
(b) The sum N5,000,000.00(Five Million Naira) as General damages for breach of contract.
(c) Interest on the said claimed at the rate of 21% per annum from the date hereof unto JUDGMENT and hereafter until final payment.”
In proof of its case, the 1st Respondent called three witnesses while the Appellant and the 2nd Respondent called three witnesses and one witness respectively. At the conclusion of the hearing, the parties were ordered to file their respective written addresses which they also adopted and relied on at the proceeding of the Court on 30/3/2006. In a judgment delivered on the 23rd day of June 2006, the trial Court granted the reliefs sought by the 1st Respondent and struck out the Appellant’s counterclaim.
The Appellant was not satisfied with the said judgment and consequently appealed to the Court of Appeal.
ISSUES FOR DETERMINATION
The Court determined the appeal on these issues couched as follows:
iii. Whether the 1st Respondent was still entitled to rental hire and not mitigate its losses having become aware that the House Boat DUFAN VI submerged on its own even before it was put to use by the Appellant.
OR
Whether the Learned Trial Judge was right when he held that the 1st Respondent is entitled to N18,000,000.00 as cost of DUFAN VI and total sum of N66,340,000.00 as hire rentals at the rate of N20,000 per day from 17/10/03 till judgment and until judgment sum is finally liquidated as well as cost of N70,000 against the Appellant which award is excessive, ridiculous high, amounts to double compensation and is based on wrong principles of law.
DECISION/HELD
On the whole, the Court found no merit in the appeal and accordingly dismissed same.
RATIOS:
Hon. Justice Sinmisola Adeniyi of the Abuja Judicial Division of the National Industrial Court has…
By Ebun-Olu Adegboruwa, SAN The main responsibility of the court is to interpret the law…
ByAmb. Hameed Ajibola Jimoh, Esq. FIGPCM, CGARB. (CERTIFIED GLOBAL PEACE AND CONFLICT RESOLUTION AND MANAGEMENT…
CASE TITLE: ORIENTAL ENERGY RESOURCES LTD v. NICON INSURANCE PLC (2024) LPELR-61988(CA) JUDGMENT DATE: 25TH…
The body of law for copyright protection in Nigeria is the Copyright Act 2022 and judicial decisions…
What is the Meaning of Indefinite Suspension? Suspension is the placement of an employee in…